27 May 2012

Day 83: Stormwater

The pipe visible in the photographs is a 160mmø stormwater pipe running through the length of our property. The purpose of this pipe is to assist in the movement of water runoff which comes from the hill on the nature reserve’s side. The pipe is bedded in soft sand and will be buried beneath the future floor slab.



03 May 2012

Day 59: Excavations 90% complete

It was such an amazing feeling, to stand in front of the newly carved driveway and to realize that I have made the right decision. The wonderful and terrible thing about this site was the beautiful big rock. You do not want to destroy even a portion of it, but you stil need to gain access. The realized concept of the driveway exceeds expectations. It created this beautiful portal leading up to the future house. I believe the building will appear slightly tucked in behind the rock and, with the planned vegetation, will subtly blend into the site.

19 April 2012

Day 45: Slow progress

Disappointingly, almost nothing has happened in the last 35 days. At least, nothing happened on site.

We went to Nepal to hike up to Everest Base Camp at 5364m above sea level. What an experience! But the most amazing thing is how sophisticated and detailed the construction methods are. With no road access and mechanical means the Nepali harvest all the building materials from the surrounding mountains. Skilled labor-intensive techniques are then used to shape the timber and stone to construct multi storey dwellings.

Currently we are waiting for a 24 ton pecker to remove some hard rock. Perhaps we can learn a thing or two about breaking rock from the mountain people.