Day 241: Progress report

To give you an overview, here is where we are now:

 • The driveway is complete
 • The basement is structurally complete
 • The basement still needs plasterwork, pipes, electrical wires, rainwater collection system, stairs, front
   door, steel sliding gate, concrete polishing
 • The ground floor slab is structurally complete
 • The ground floor walls are starting to go up
 • The ground floor still needs walls, stone, braai, fireplace, internal doors, windows, aluminium doors,
    structural steel columns, concrete polishing and kitchen fit out
 • Then the whole first floor and the roof still need to be built.

It is a slow process…