29 April 2013
Day 431: Last minute defects
At 7am last Wednesday morning I did my “final” inspection.
The concrete pump and concrete trucks were all scheduled to arrive at 9am. I
have been inspecting electrical conduits, drainage pipes, storm water details
and shutter boards all week and thought that everything was in place. I was just
about to leave when a saw a detail right at the edge of the slab that was
COMPLETELY WRONG. It was a detail changed by the contractor in order to save
time during casting, and the result was entirely different from the original
design. As a result, we had to cancel the concrete and delay the pouring until
this week Friday.
12 April 2013
11 April 2013
09 April 2013
Day 411: Concrete surface finish
We discovered a specialist who does fantastic work with
concrete. Have a look at the texture on the shutter boards. The fine timber
grain will be etched into the finished surface of the concrete.
Here are a few examples of other houses done by this specialist.
The large shutter boards used for the ceilings and beams will generate a smooth timber grained effect similar to these photographs.
08 April 2013
Day 410: Concrete tables
Do you remember the post below about the steel details…well
here they are cast into concrete slabs. These slabs are currently being built
into the outside area where the braai will be.
As for progress, most of the shutter work is in place and
ready for the casting of the first floor slab. The next step is the
installation of the plumbing, electrical conduits and steel reinforcement.
There after the concrete pump mix can be ordered and the casting can begin.