29 October 2012
25 October 2012
Day 234: Incorrect slope
Imagine my surprise when we arrived on site on Saturday and
found water dammed up on our southern patio. Friday night’s rain revealed the
incorrect slope of the exterior slab.
19 October 2012
Day 228: Concrete details
The shutter boards were removed, exposing all the details
designed into the concrete slab.
Drip joint at the edge of the slab
Aluminium channel to receive a LED light strip
Concrete column to brick wall connection
The light at the end of the tunnel is where the wine cellar
is...
18 October 2012
Day 227: Paved driveway
The concrete slabs in between the pavement prevents the
paving stones from gradually sliding down the hill.
Steel box for water meter
17 October 2012
Day 226: Concrete grinding and polishing
This is the first step in the process of obtaining a polished
concrete floor finish. A few millimeters are grinded off to expose the aggregate.
At a later stage another layer will be grinded off until the final finished
floor level is reached. The concrete is
then polished several times and sealed with a deep penetrating sealer.
16 October 2012
10 October 2012
Day 219: Curing concrete
After casting, the concrete was covered with a plastic sheet
to assist the curing process. We removed the sheet on Monday to have a look at
our slab.
03 October 2012
Day 212: Casting of ground floor slab
On photographs everything looks so calm and in control. In
reality however…the site was in total chaos. The concrete was supposed to
arrive at 8am. Instead, we were all running around until 12pm installing drainage,
tying down steel mesh, fixing shutter boards and getting serious sunburn.
Finally when everything was in place the concrete pouring
could start. They poured the balconies first. The concrete mixture contained a
waterproofing admixture mixed into the concrete prior to delivery.
As they pour, someone directs the flow, someone else vibrates
the concrete, another person starts levelling and before you know it you have a
ground floor slab complete with electrical conduits and plumbing pipes.
01 October 2012
Day 210: The night before casting
The site was covered with people this afternoon, scurrying to ready everything for tomorrow’s casting of the slab. Yet, it is not quite right…
Subscribe to:
Posts (Atom)